Calculating the ROI of on-site nitrogen generation
Switching from delivered nitrogen cylinders to an on-site nitrogen generator can transform a company's bottom line. This real-world example from a manufacturer in the Czech Republic shows how investing in an all-in-one nitrogen solution not only reduced their operational costs dramatically but also paid for itself in under a year.
Here’s a closer look at how they made it happen:
Customer profile:
- Nitrogen consumption: 29 Nm³/hour
- Operating hours: 5,586 hours/year
- Estimated annual nitrogen usage: 162,994 Nm³
- Solution installed: PPNG 11 skid HE all-in-one nitrogen generation system
Cost analysis: Delivered nitrogen vs. on-site generation
Delivered nitrogen costs
- Annual delivered nitrogen cost: 8,099,700 CZK (approx. €324,400
- Effective cost per Nm³: 49.69 CZK (approx. €2.00)
On-site generation costs (PPNG 11 Skid HE)
- Annual electricity cost: 574,280 CZK (approx. €23,000)
- Annual service cost: 309,000 CZK (approx. €12,400)
- Total annual operating cost: 883,280 CZK (approx. €35,300
- Effective generation cost per Nm³: 5.42 CZK (approx. €0.22)
|
Delivered nitrogen |
On-site generation |
---|
Annual Cost (CZK) |
8,099,700 CZK |
883,280 CZK |
Cost per Nm³ (CZK) |
49.69 CZK |
5.42 CZK |
Annual Cost (EUR) |
€324,400 |
€35,300 |
Cost per Nm³ (EUR) |
€2.00 |
€0.22 |
Annual Savings (CZK) |
7,216,420 CZK |
|
Annual Savings (EUR) |
€289,100 |
|
Payback period
- Initial investment: 4,761,428 CZK (approx. €190,500)
- Annual savings: 7,216,420 CZK (approx. €289,100)
Payback period = Initial investment ÷ annual savings
= 4,761,428 ÷ 7,216,420 = 0.66 years = Approximately 8 months
Five-year financial impact
Projected savings over five years:
36,082,100 CZK (approx. €1,445,500)
Beyond the short payback period, the financial gains continue to accumulate year after year, making the investment exceptionally attractive.